Drywall Progress
The Drywall: October 17 - November 17, 2003
The drywall was delivered Friday October 17th
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Thursday October 23 the most
important room in the house is being dry walled:
the garage!!!............
![]() |
![]() |
and the laundry ceiling.....
Monday October 27 the dry walling of the house has began! |
|
|
|
| Monday
November 3rd the dry wall work went full steam ahead......... |
|
|
|
|
|
C.B. is working away! |
|
|
|
| Erv working on Saturday November 8!!!!! | |
|
|
Saturday November 15, preparing for the orange peel! |
Monday November 17 textured the walls orange peel. Dry wall all pau! |
|
Tuesday, November 18 primed!
Wednesday, November 19 painted!. |