1051 Puu Rd. Kalaheo, Kauai
Drywall Progress

 

The Drywall: October 17 - November 17, 2003

The drywall was delivered Friday October 17th

in the meantime Tuesday October 21st Andrea got stuck......
and EJ came to the rescue............

Thursday October 23 the most important room in the house is being dry walled:
the garage!!!............


and the laundry ceiling.....

Monday October 27 the dry walling of the house has began!

Monday November 3rd 
the dry wall work went full steam ahead.........

C.B. is working away!

Erv working on Saturday November 8!!!!!

Saturday November 15, 
preparing for the orange peel!
 
Monday November 17 textured the walls
orange peel. 
Dry wall all pau!

Painters: November 18 - November 19, 2003
Tuesday, November 18 primed!

Wednesday, November 19 painted!.
Painters all pau!

 

Construction ] Framing ] Walls ] Roof ] Siding ] Plumbing Electrical ] [ Drywall ] Concrete work ] Inside ] Decks ] Moving ] Blessing ] Interiors ] Garden ] Views ]