Flooring Progress

The floors:  ..................... 2003

Friday, November 14th the maple has been delivered!

Wednesday 3rd the work starts......


Konrad coordinates with Desdree!

Monday December 8 the maple goes down!

Tuesday December 23 all the maple is installed.

February 3 the sanding and sealing starts!

February 10th the 4th coat has been applied. 
The maple hardwood floors are all pau!