1051 Puu Rd. Kalaheo, Kauai
Plumbing and Electrical Progress

 

Plumbing work: September 9 - October 3, 2003

and electrical: September 29 - October 10, 2003

Tuesday, September 9 they started the plumbing!

Friday October 3rd the plumbing was completed and passed inspection Monday October 6th!!!

 

 

 

 

 

 

 

Monday September 29 the electrical work started and on Friday October 10th was finished and inspected!

 Cables, cables, cables.............

 

 December 4th the swim spa is ready to be tested.............

End of February...

Randall at work.........

All Pau March 55h!


Construction ] Framing ] Walls ] Roof ] Siding ] [ Plumbing Electrical ] Drywall ] Concrete work ] Inside ] Decks ] Moving ] Blessing ] Interiors ] Garden ] Views ]